The new Florida Building Code takes effect December 31, and one section lands straight on the metal scope.
New Section 1711 requires corrosion-resistant fasteners, connectors and plates within 3,000 feet of a saltwater coastline. Inside 300 feet and exposed, fasteners have to be stainless. From 300 feet out to 3,000 feet it is stainless or enhanced galvanizing, depending on how exposed the assembly is. What is covered is the hardware that ties the metal to the structure: anchors, bolts, lag screws, clips, straps and plates.
For Broward, Miami-Dade and Palm Beach, that reaches a lot of the work we all have on the boards. And it is the kind of requirement that turns into a substitution request in the field when nobody priced it at buyout.
Three things worth doing now.
Check the distance from the coastline, not the distance to the water view. The 3,000-foot band is wide enough to catch plenty of buildings that do not feel coastal.
Confirm which edition governs the permit. Applications first submitted on or after December 31 fall under the new code. Miami-Dade RER has said portal submissions after 4 p.m. on December 30 will be reviewed under the 2026 edition, so on a project that is close, the filing date is the whole ballgame.
Price the finish, not just the part. Stainless and enhanced galvanized hardware costs more and takes longer to source. Better in the quote than in a change order three months in.
We are quoting coastal miscellaneous metals to the new section now, and glad to walk through what it means for a specific job.
Which hardware specs are you already seeing called out on drawings?