Another successful structural lining installation completed by the team today.
We installed 32m of 100mm continuous structural liner for a domestic customer. Following our CCTV survey, the pipeline was found to have structural defects throughout its entire length, making a single continuous installation the best long-term solution rather than multiple liner sections.
With the temperatures we’re currently experiencing, this was a particularly challenging installation. Anyone familiar with CIPP lining knows how quickly resin can begin to cure in hot weather, so careful planning was essential. The liner was kept continuously wet to maintain a lower temperature until it was in position and ready for installation.
Despite the conditions, the team delivered another high-quality no-dig repair, restoring the structural integrity of the pipeline with minimal disruption to the customer.
Excellent work by everyone involved.