We snuck in one more before the weather turned,this one happened to be for my lovely sister Vanessa Dirsten Im excited to see it with house and decks moved in. It will also be nice to finish up the landscaping in the spring!
This job entailed
●STRIPPED TOP SOIL
● BUILDING UP HOUSE PAD INTO HILL SIDE, -packed in 6" lifts
● 2" CRUSHED BASE, CAPLED WITH 3/4" CAP
●SEPTIC DESIGN SOIL SAMPLES ECT.
● MOVED OPEN DISCHARGE FROM OTHER HOME TO REQUIRED SET BACK
●INSTALLED ENTIRE SEPTIC SYSTEM
- Tank with 5' of cover
- open discharge 8' delivery line for frist prevention.
-Open discharge fenched in mounded up and capped with feild stone.
- delivery line sloped to perfection,in ideal location.
● 380 FEET OF WATER LINE INSTALLED
- 8'+ trench.
- High end water line
-Brass fittings for longevity
-Heat trase top end to ensure no freezing until tide into home.
● LAST BUT LEAST DRAAINAGE!!
-Sloped back the cut
-cut in swales around pad and away from home and yard.